The work to be done consists of furnishing all materials, equipment, and labor necessary to construct Adkins 60” Potable Water Transmission Main Phase 2, consisting of the following:
Excavation, installation, and backfill of 32,017 ft of 60-inch welded steel pipe transmission main.
Installation of 1,072 ft of 72-inch steel casing by jack and bore across four separate bores, including two river bores and two roadway bores. The jack-and-bore work used a 72-inch Robbins MSBU.
Three connections tying the new 60-inch welded steel pipe to the existing 72-inch PCCP transmission main.